High Pressure Service |
Low Pressure Service |
|
Engines
Main Station
Holly Mfg. Co.
Triple expansion engines
25,828,000 G.P.D. pump
1200 HP, 153,890,000 work,
GCWW, 10-6-1906 /12-2-1952
 |
3 @ 12,000,000 GPD
Head 412' to 506' |
4 @ 25,000,000 GPD,
Head 154' to 225' |
|
Manufacture |
Holly Mfg Co., Lockport, NY |
|
Holly history |
Holly Manufacturing Company began in
Lockport NY, merged with the Snow Steam Pump Works of
Buffalo NY, and became part of International Steam. Later
they became Worthington Pump headquartered in Buffalo and
closed in 1987.
source |
|
Type |
Vertical, triple expansion, crank & flywheel |
|
Construction |
1898-1906 |
|
|
Service |
10-6-1906 / 12-2-1952 |
|
|
High pressure cylinder |
34" diameter |
32" diameter |
|
Intermediate pressure cylinder |
64" diameter |
60" diameter |
|
Low pressure cylinder |
98" diameter |
90" diameter |
|
Stroke |
60" |
60" |
|
Steam pressure |
160 p.s.i. |
160 p.s.i. |
|
Surface area of 1st
re-heater |
165 ft2 |
157 ft2 |
|
Surface area of 2nd
re-heater |
230 ft2 |
285 ft2 |
|
Steam valve gearing |
Corliss & Poppet |
Corliss & Poppet |
|
R.P.M. |
20 nominal |
20 nominal |
|
Piston speed |
200 feet/minute |
200 feet/minute |
|
Horse power |
1,100 Mfg |
1,200 |
|
Flywheels |
2 |
2 |
|
Flywheel |
20' diameter, 38 ton |
20' diameter, 35 ton |
|
Length of main shaft |
12' 7 1/2" |
12' 1 1/2" |
|
Diameter of main shaft |
23 3/8" |
22" |
|
Length of main shaft journals |
32" |
32" |
|
Diameter of main shaft journals |
20" |
19" |
|
Length of crank pin journal |
11" |
11" |
|
Diameter of crank pin journal |
12 1/2" |
12" |
|
Length of cross head pin journal |
11" |
11" |
|
Diameter cross head pin journal |
12 1/2" |
12" |
|
Weight |
1,100 ton |
900 |
|
Height |
57 feet |
|
|
Base |
21' 6" deep X wide x high |
|
|
Working decks |
6 decks |
|
|
Attached Ancillaries |
Attached surface condenser, air pump, feed pump, air
compressor, exhaust heater |
|
Condenser type |
Surface |
Surface |
|
Condenser size |
5' 11" x 13' 6' |
5' 11" x 12' 6' |
|
Condensing surface |
2,200 ft2 |
2,000 ft2 |
|
Diameter of attached air pump cylinder |
24" |
24" |
|
Stroke of air pump piston |
60" |
60" |
|
Diameter of feed pump cylinder |
3 1/4" |
3 1/4" |
|
Stroke of feed pump plunger |
60" |
60" |
|
Diameter of attached air compressor cylinder |
3 3/8" |
3 3/8" |
|
Auxiliary air compressor |
New York Air Brake Company |
|
Diameter of air compressor piston |
two-stage, 2 1/2" and 3" |
single-stage, 3" |
|
Stroke of air compressor piston |
60" |
60" |
|
Heating surface of exhaust heater |
314 ft2 |
314 ft2 |
|
Pumps |
|
|
|
Pumps/engine |
3 |
3 |
|
Pump type |
Plunger |
Plunger |
|
Pump plunger diameter |
26 1/2" |
38 1/4" |
|
Diameter of pump barrel |
38" |
55" |
|
Diameter of pump valve chamber |
59" |
61" |
|
Effective area of pump valves |
824 ft2 |
1,440 ft2 |
|
Diameter of valves |
3 5/8" |
4 3/16" |
|
Diameter of discharge |
Dual 22" |
Dual 30" |
|
Pumping capacity/engine GPD*** |
12,000,000 rated
12,435,222 tested |
25,000,000 rated
25,828,539 tested |
|
Gallons/Revolution |
428 |
890 |
|
Stroke |
60 inches |
60 inches |
|
Inlet nozzle |
60" |
72" |
|
Outlet nozzle |
48" |
60" |
|
Discharge pressure |
220 p.s.i. |
97 p.s.i. |
|
Suction valves |
3 5/8 inch diameter |
|
|
Discharge valves |
4 3/16 inch diameter |
|
|
Boilers |
|
|
|
Boilers
Geary water tube boilers
by Oil City Boiler Works
replaced with Stirling water tube boilers 1921-1923
 |
Six batteries of two each, Geary water
tube boilers by Oil City Boiler Works. In 1921-23 the
boilers were replaced with seven Stirling water tube
boilers, 529 HP each and Riley forced draught stokers. |
|
Boiler plant HP |
3,703 |
|
|
Boiler plant efficiency |
74% |
71.8% |
|
Boiler tubes |
140 tubes, 3 1/2 inch diameter |
|
Boiler feed pumps |
2- pumps from the Snow Steam Pump Company |
|
Feed water heater |
Erie City Iron Works |
|
|
Coal feed |
American underfeed stokers |
|
|
Steam pressure |
160 p.s.i.g. |
|
|
Steam moisture |
1% at engine, 2% at boiler |
|
|
Heat boosters |
|
|
|
Gases leaving boiler |
523°F |
|
|
Gases leaving superheater |
|
|
|
Stack temperature |
235°F |
|
|
Water evaporated per 1 lb dry coal |
9.47 lb, boiler contribution 95%, economizer contribution 5% |
9.23 |
|
Feed water |
82°F from water softening and
deaerating plant , 124° from
engine heater , 201°F
from auxiliary heater , 259°F from
economizer |
|
Work duty coal for every 100 lb of dry coal |
135,000,000 ft lb rated
152,884,425 ft lb, tested |
135,000,000 ft lb rated
153,889,966 ft lb tested |
|
Work duty steam |
173,560,148 ft lb per 1,000 lb of dry steam, weir
measurement |
172,650,715 ft lb |
|
Boiler House |
|
|
Smokestack |
Dual 8' ID, 150' high stacks of brick on
circular stone base resting on a concrete foundation with a
diameter of 35' and 8' deep. The stack is faced with light
buff-colored radial Kittanning pressed brick and toped with
a cast-iron cap.
Forced draught was provided by two 10 inch by 10 inch
Buffalo Forge Co. engines each direct driving an 92 inch
Buffalo Forge Co. fan. |
|
Coal storage building |
|
|
Coal storage |
8,400 tons allowing for an ample supply during periods of
low river level. |
|
Coal hoppers |
120, inverted pyramid (pocket type) storing 70 ton/hopper |
|
Coal supply |
Coal supply was originally received by barge |
|
Coal delivery |
Coal was elevated to a cross belt conveyor and distributed
by means of shuttle belt conveyors to the 120 pocket
hoppers. |
|
Boiler coal delivery (Coal Passers) |
Coal was delivered to the boilers via a wagon pulled by an
electric battery driven engine called the "Dingy" about the
size of a golf cart. |
|
Coal size |
Pittsburg Nut & Slack which is 1 1/2" and 3/4" respectively.
13,000 B.T.U. per pound of coal |
|
Coal moisture |
2 1/3% |
|
|
Ash from coal |
9.45 % |
|
|
Slate in coal |
.55% |
|
|
Station Electrical Supply |
Four Crocker-Wheeler 40 K.W. four-pole generators powered by
two De Laval steam turbines with an operating of speed of
1,200 RPM, supplied by Dravo, Doyle & Co., Sewickley, PA. at
a cost of $8,650- |
|
* * * GPD, Gallons Per day |
|
|